Arizona Public Service Queue Project Q534 — Solar+Battery in Navajo Az, the U.S.

Arizona Public Service Queue Project Q534 — Solar+Battery in Navajo Az, the U.S. is a 60.0 MW solar+battery interconnection project with a current status of active. It is proposed to connect at Line off the to Saguaro Line.

60.0 MWCapacity
ActiveStatus
Market
Solar+BatteryTechnology

Project facts

Canonical nameArizona Public Service Queue Project Q534 — Solar+Battery in Navajo Az, the U.S.
Queue IDQ534
Statusactive
Source status(Draft) Interconnection Cluster: Energy
Market
TechnologySolar+Battery
Capacity60.0 MW
State
CountyNavajo Az
Point of interconnectionLine off the to Saguaro Line
Requested (queue) date2023-04-04
Proposed in-service date2026-12-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerArizona Public Service

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-10poi_name69 kV Line New substation off the Milligan to Saguaro LineLine off the to Saguaro Linelow
2026-08-10proposed_online_date2026-12-31medium
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: aps-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata