Arizona Public Service Queue Project Q554 — Battery in Pinal Az, the U.S.

Arizona Public Service Queue Project Q554 — Battery in Pinal Az, the U.S. is a 200.0 MW battery interconnection project with a current status of active. It is proposed to connect at 230 kV.

200.0 MWCapacity
ActiveStatus
Market
BatteryTechnology

Project facts

Canonical nameArizona Public Service Queue Project Q554 — Battery in Pinal Az, the U.S.
Queue IDQ554
Statusactive
Source statusStudy Phase 2 Interconnection Start of Network
Market
TechnologyBattery
Capacity200.0 MW
State
CountyPinal Az
Point of interconnection230 kV
Requested (queue) date2024-05-02
Proposed in-service date2030-03-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerArizona Public Service

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-10poi_nameBianco 230 kV230 kVlow
2026-08-10phaseStudylow
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-28

Provenance: aps-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata