Arizona Public Service Queue Project Q599 — Solar+Battery in Yuma Az, the U.S. is a 500.0 MW solar+battery interconnection project with a current status of active.

500.0 MWCapacity
ActiveStatus
—Market
Solar+BatteryTechnology

Project facts

Canonical nameArizona Public Service Queue Project Q599 — Solar+Battery in Yuma Az, the U.S.
Queue IDQ599
Statusactive
Source statusUpdated Deposit Interconnection
Market—
TechnologySolar+Battery
Capacity500.0 MW
State—
CountyYuma Az
Point of interconnection—
Requested (queue) date2025-05-14
Proposed in-service date2031-12-31
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerArizona Public Service

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-10poi_name500 kV line—low
2026-08-03new_project—activehigh

Explore related data

Source last checked2026-11-23
Data last materially changed2026-09-14
Page data generated2026-11-26

Provenance: aps-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata