Arizona Public Service Queue Project Q608 — Solar+Battery in Pinal Az, the U.S.

Arizona Public Service Queue Project Q608 — Solar+Battery in Pinal Az, the U.S. is a 55.0 MW solar+battery interconnection project with a current status of active. It is proposed to connect at TS25 at gen-tie double circuit 345 at the posts and 150/3 with the to move existing (capacitor which is currently approx. 3,500.

55.0 MWCapacity
ActiveStatus
Market
Solar+BatteryTechnology

Project facts

Canonical nameArizona Public Service Queue Project Q608 — Solar+Battery in Pinal Az, the U.S.
Queue IDQ608
Statusactive
Source status1 Cluster Study Interconnection Start of Network
Market
TechnologySolar+Battery
Capacity55.0 MW
State
CountyPinal Az
Point of interconnectionTS25 at gen-tie double circuit 345 at the posts and 150/3 with the to move existing (capacitor which is currently approx. 3,500
Requested (queue) date2025-05-16
Proposed in-service date2028-12-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerArizona Public Service

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-10poi_nameSundance 230kV APS transmission line New substation at gen- tie of the double circuit 345 kV lines at the posts 149/4 and 150/3 with the request to move existing switchyard (capacitor bank) which is currently located approx. 3,500TS25 at gen-tie double circuit 345 at the posts and 150/3 with the to move existing (capacitor which is currently approx. 3,500low
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: aps-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata