Arizona Public Service Queue Project Q671 — Battery in Pinal Az, the U.S.

Arizona Public Service Queue Project Q671 — Battery in Pinal Az, the U.S. is a 140.0 MW battery interconnection project with a current status of active. It is proposed to connect at tap on 69 kV Toyota.

140.0 MWCapacity
ActiveStatus
Market
BatteryTechnology

Project facts

Canonical nameArizona Public Service Queue Project Q671 — Battery in Pinal Az, the U.S.
Queue IDQ671
Statusactive
Source status1 Cluster Study Interconnection Start of Energy
Market
TechnologyBattery
Capacity140.0 MW
State
CountyPinal Az
Point of interconnectiontap on 69 kV Toyota
Requested (queue) date2026-05-18
Proposed in-service date2030-03-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerArizona Public Service

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-10poi_name230 kV Requested POI N/A - line tap on 69 kV line between Toyotatap on 69 kV Toyotalow
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: aps-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.