Arizona Public Service Queue Project Q674 — Solar+Battery in Yuma Az, the U.S.

Arizona Public Service Queue Project Q674 — Solar+Battery in Yuma Az, the U.S. is a 600.0 MW solar+battery interconnection project with a current status of active. It is proposed to connect at 69 kV SS Wash 500kV.

600.0 MWCapacity
ActiveStatus
Market
Solar+BatteryTechnology

Project facts

Canonical nameArizona Public Service Queue Project Q674 — Solar+Battery in Yuma Az, the U.S.
Queue IDQ674
Statusactive
Source status1 Cluster Study Interconnection Request: In Request: In Energy Interconnection LGIA Energy
Market
TechnologySolar+Battery
Capacity600.0 MW
State
CountyYuma Az
Point of interconnection69 kV SS Wash 500kV
Requested (queue) date2026-05-18
Proposed in-service date2029-10-10
Operational date
Withdrawn date
Developer
Utility / transmission ownerArizona Public Service

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-10poi_nameOrchard69 kV SS Wash 500kVlow
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: aps-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.