Proposed 345kV Substation on the Wichita to Thistle 345kV line, circuits 1 & 2 (GEN-2015-043)

Proposed 345kV Substation on the Wichita to Thistle 345kV line, circuits 1 & 2 is a 20.0 MW battery interconnection project in Pratt County, Kansas with a current status of withdrawn. It is proposed to connect at Proposed 345kV Substation on the Wichita to Thistle 345kV line, circuits 1 & 2.

20.0 MWCapacity
WithdrawnStatus
KSMarket
BatteryTechnology

Project facts

Canonical nameProposed 345kV Substation on the Wichita to Thistle 345kV line, circuits 1 & 2
Queue IDGEN-2015-043
Statuswithdrawn
Source statusWITHDRAWN
MarketKS
TechnologyBattery
Capacity20.0 MW
StateKansas
CountyPratt County
Point of interconnectionProposed 345kV Substation on the Wichita to Thistle 345kV line, circuits 1 & 2
Requested (queue) date2015-10-05
Proposed in-service date
Operational date
Withdrawn date2016-03-16
Developer
Utility / transmission ownerWERE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.