Ratcliffe (57037_1C)

Ratcliffe is a 369.0 MW gas interconnection project in Kemper, Mississippi with a current status of operational.

369.0 MWCapacity
OperationalStatus
SOCOMarket
GasTechnology

Project facts

Canonical nameRatcliffe
Queue ID57037_1C
Statusoperational
Source status(OP) Operating
MarketSOCO
TechnologyGas
Capacity369.0 MW
StateMississippi
CountyKemper
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date2014-08-01
Withdrawn date—
Developer—
Utility / transmission ownerMississippi Power Co

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—operationalhigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.