Roadrunner 345kV (GEN-2014-030)
Roadrunner 345kV is a 150.0 MW solar interconnection project in Lea County, New Mexico with a current status of withdrawn. It is proposed to connect at Roadrunner 345kV.
150.0 MWCapacity
WithdrawnStatus
NMMarket
SolarTechnology
Project facts
| Canonical name | Roadrunner 345kV |
|---|---|
| Queue ID | GEN-2014-030 |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | NM |
| Technology | Solar |
| Capacity | 150.0 MW |
| State | New Mexico |
| County | Lea County |
| Point of interconnection | Roadrunner 345kV |
| Requested (queue) date | 2014-09-25 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | 2015-02-05 |
| Developer | — |
| Utility / transmission owner | SPS |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.