Roaring Brook is a 79.9 MW wind interconnection project in Lewis, New York with a current status of withdrawn. It is proposed to connect at Adirondak-Porter 230kV.

79.9 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameRoaring Brook
Queue ID0196
Statuswithdrawn
Source status0
Market
TechnologyWind
Capacity79.9 MW
StateNew York
CountyLewis
Point of interconnectionAdirondak-Porter 230kV
Requested (queue) date2005-07-01
Proposed in-service date2006-07-10
Operational date
Withdrawn date
DeveloperRoaring Brook Windpower, LLC
Utility / transmission ownerNM-NG

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.