Rock Creek 345 kV is a 150.0 MW generation interconnection project with a current status of operational. It is proposed to connect at Rock Creek 345 kV.

150.0 MWCapacity
OperationalStatus
Market
GenerationTechnology

Project facts

Canonical nameRock Creek 345 kV
Queue IDS1087
Statusoperational
Source statusActive
Market
TechnologyGeneration
Capacity150.0 MW
State
CountyClinton
Point of interconnectionRock Creek 345 kV
Requested (queue) date2025-02-18
Proposed in-service date2026-06-01
Operational date2026-06-01
Withdrawn date
Developer
Utility / transmission ownerITC MIDWEST

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.