Roosevelt substation 230kV (GEN-2016-086)

Roosevelt substation 230kV is a 240.0 MW solar interconnection project in Roosevelt, New Mexico with a current status of withdrawn. It is proposed to connect at Roosevelt substation 230kV.

240.0 MWCapacity
WithdrawnStatus
NMMarket
SolarTechnology

Project facts

Canonical nameRoosevelt substation 230kV
Queue IDGEN-2016-086
Statuswithdrawn
Source statusWITHDRAWN
MarketNM
TechnologySolar
Capacity240.0 MW
StateNew Mexico
CountyRoosevelt
Point of interconnectionRoosevelt substation 230kV
Requested (queue) date2016-06-30
Proposed in-service date
Operational date
Withdrawn date2017-03-28
Developer
Utility / transmission ownerSPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata