Salt River Substation 138kV (S1032)

Salt River Substation 138kV is a 90.0 MW generation interconnection project with a current status of operational. It is proposed to connect at Salt River Substation 138kV.

90.0 MWCapacity
OperationalStatus
Market
GenerationTechnology

Project facts

Canonical nameSalt River Substation 138kV
Queue IDS1032
Statusoperational
Source statusActive
Market
TechnologyGeneration
Capacity90.0 MW
State
CountyIsabella County
Point of interconnectionSalt River Substation 138kV
Requested (queue) date2022-08-19
Proposed in-service date2025-07-30
Operational date2025-07-30
Withdrawn date
Developer
Utility / transmission ownerMETC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.