SALT RIVER - WARREN 138.0kV (J3940)

SALT RIVER - WARREN 138.0kV is a 214.0 MW solar interconnection project in Isabella, Michigan with a current status of withdrawn. It is proposed to connect at SALT RIVER - WARREN 138.0kV.

214.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameSALT RIVER - WARREN 138.0kV
Queue IDJ3940
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity214.0 MW
StateMichigan
CountyIsabella
Point of interconnectionSALT RIVER - WARREN 138.0kV
Requested (queue) date2025-02-14
Proposed in-service date2030-06-01
Operational date2030-06-01
Withdrawn date2026-04-15
Developer
Utility / transmission ownerMETC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata