SC Queue Project 234 — Battery in Hampton, South Carolina

SC Queue Project 234 — Battery in Hampton, South Carolina is a 75.0 MW battery interconnection project in Hampton, South Carolina with a current status of active. It is proposed to connect at Varnville 230 kV Bus.

75.0 MWCapacity
ActiveStatus
SCMarket
BatteryTechnology

Project facts

Canonical nameSC Queue Project 234 — Battery in Hampton, South Carolina
Queue ID234
Statusactive
Source status2023 Cluster
MarketSC
TechnologyBattery
Capacity75.0 MW
StateSouth Carolina
CountyHampton
Point of interconnectionVarnville 230 kV Bus
Requested (queue) date2023-06-01
Proposed in-service date2027-10-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerSouth Carolina Public Service Authority (Santee Cooper)

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: santee-cooper-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata