SC Queue Project 347 — Gas in Hampton, South Carolina

SC Queue Project 347 — Gas in Hampton, South Carolina is a 457.6 MW gas interconnection project in Hampton, South Carolina with a current status of withdrawn. It is proposed to connect at N/A.

457.6 MWCapacity
WithdrawnStatus
SCMarket
GasTechnology

Project facts

Canonical nameSC Queue Project 347 — Gas in Hampton, South Carolina
Queue ID347
Statuswithdrawn
Source statusWithdrawn
MarketSC
TechnologyGas
Capacity457.6 MW
StateSouth Carolina
CountyHampton
Point of interconnectionN/A
Requested (queue) date2026-04-01
Proposed in-service date2035-01-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerSouth Carolina Public Service Authority (Santee Cooper)

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-24statusactivewithdrawnhigh
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: santee-cooper-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata