Seward 115 kV Substation is a 80.0 MW solar interconnection project in Stafford, Kansas with a current status of withdrawn. It is proposed to connect at Seward 115 kV Substation.

80.0 MWCapacity
WithdrawnStatus
KSMarket
SolarTechnology

Project facts

Canonical nameSeward 115 kV Substation
Queue IDGEN-2024-007
Statuswithdrawn
Source statusWITHDRAWN
MarketKS
TechnologySolar
Capacity80.0 MW
StateKansas
CountyStafford
Point of interconnectionSeward 115 kV Substation
Requested (queue) date2024-04-30
Proposed in-service date2028-12-31
Operational date
Withdrawn date2026-05-21
Developer
Utility / transmission ownerMIDW

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.