Sharpe (7973_4)

Sharpe is a 2.0 MW other interconnection project in Coffey, Kansas with a current status of operational.

2.0 MWCapacity
OperationalStatus
SWPPMarket
OtherTechnology

Project facts

Canonical nameSharpe
Queue ID7973_4
Statusoperational
Source status(OP) Operating
MarketSWPP
TechnologyOther
Capacity2.0 MW
StateKansas
CountyCoffey
Point of interconnection
Requested (queue) date
Proposed in-service date
Operational date2002-07-01
Withdrawn date
Developer
Utility / transmission ownerKansas Electric Power Coop Inc

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_projectoperationalhigh

Explore related data

Source last checked2026-08-03
Data last materially changed2026-08-03
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.