Slate Goss 345 KV Line (J2813)

Slate Goss 345 KV Line is a 195.0 MW solar interconnection project in Saginaw, Michigan with a current status of withdrawn. It is proposed to connect at Slate Goss 345 KV Line.

195.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameSlate Goss 345 KV Line
Queue IDJ2813
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity195.0 MW
StateMichigan
CountySaginaw
Point of interconnectionSlate Goss 345 KV Line
Requested (queue) date2022-09-13
Proposed in-service date2027-02-15
Operational date2027-02-15
Withdrawn date2023-03-24
Developer
Utility / transmission ownerMETC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.