Smithville 161 kV Substation (GEN-2024-090)

Smithville 161 kV Substation is a 100.0 MW battery interconnection project in Clay, Missouri with a current status of operational. It is proposed to connect at Smithville 161 kV Substation.

100.0 MWCapacity
OperationalStatus
MOMarket
BatteryTechnology

Project facts

Canonical nameSmithville 161 kV Substation
Queue IDGEN-2024-090
Statusoperational
Source statusDISIS STAGE
MarketMO
TechnologyBattery
Capacity100.0 MW
StateMissouri
CountyClay
Point of interconnectionSmithville 161 kV Substation
Requested (queue) date2024-10-30
Proposed in-service date
Operational date2028-02-15
Withdrawn date
Developer
Utility / transmission ownerWERE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.