Smoky Hills Tap 230kV (GEN-2003-019)

Smoky Hills Tap 230kV is a 249.3 MW wind interconnection project in Salina Nc Ellsworth Cnty, Kansas with a current status of operational. It is proposed to connect at Smoky Hills Tap 230kV.

249.3 MWCapacity
OperationalStatus
KSMarket
WindTechnology

Project facts

Canonical nameSmoky Hills Tap 230kV
Queue IDGEN-2003-019
Statusoperational
Source statusIA FULLY EXECUTED/COMMERCIAL OPERATION
MarketKS
TechnologyWind
Capacity249.3 MW
StateKansas
CountySalina Nc Ellsworth Cnty
Point of interconnectionSmoky Hills Tap 230kV
Requested (queue) date2003-11-24
Proposed in-service date
Operational date2006-11-01
Withdrawn date
Developer
Utility / transmission ownerMIDW

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.