Solar (660)

Solar is a 20.0 MW solar interconnection project in Windham, Vermont with a current status of withdrawn. It is proposed to connect at National Grid line tap 69 kV transmission line (D-4), feeding the Vernon Station No. 13.

20.0 MWCapacity
WithdrawnStatus
NHMarket
SolarTechnology

Project facts

Canonical nameSolar
Queue ID660
Statuswithdrawn
Source statusW
MarketNH
TechnologySolar
Capacity20.0 MW
StateVermont
CountyWindham
Point of interconnectionNational Grid line tap 69 kV transmission line (D-4), feeding the Vernon Station No. 13
Requested (queue) date2017-07-20
Proposed in-service date2022-07-01
Operational date
Withdrawn date2020-09-10
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata