SPS Erskine Substation 115 kV (ASGI-2017-007)

SPS Erskine Substation 115 kV is a 4.2 MW wind interconnection project with a current status of withdrawn. It is proposed to connect at SPS Erskine Substation 115 kV.

4.2 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameSPS Erskine Substation 115 kV
Queue IDASGI-2017-007
Statuswithdrawn
Source statusWITHDRAWN
Market
TechnologyWind
Capacity4.2 MW
State
County
Point of interconnectionSPS Erskine Substation 115 kV
Requested (queue) date2017-06-02
Proposed in-service date2019-01-31
Operational date
Withdrawn date2020-10-22
Developer
Utility / transmission ownerSPS

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata