SR McNeal (66925_MCBA)

SR McNeal is a 20.0 MW battery interconnection project in Cochise, Arizona with a current status of operational.

20.0 MWCapacity
OperationalStatus
TEPCMarket
BatteryTechnology

Project facts

Canonical nameSR McNeal
Queue ID66925_MCBA
Statusoperational
Source status(OP) Operating
MarketTEPC
TechnologyBattery
Capacity20.0 MW
StateArizona
CountyCochise
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date2023-12-01
Withdrawn date—
Developer—
Utility / transmission ownerSR McNeal, LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—operationalhigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-11

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata