ST70S Project is a 70.0 MW solar+battery interconnection project in Dona Ana, New Mexico with a current status of withdrawn. It is proposed to connect at Santa Teresa 115 kV substation.

70.0 MWCapacity
WithdrawnStatus
WestMarket
Solar+BatteryTechnology

Project facts

Canonical nameST70S Project
Queue IDLG-17-9-5
Statuswithdrawn
Source statuswithdrawn
MarketWest
TechnologySolar+Battery
Capacity70.0 MW
StateNew Mexico
CountyDona Ana
Point of interconnectionSanta Teresa 115 kV substation
Requested (queue) date2017-09-27
Proposed in-service date2021-06-01
Operational date
Withdrawn date2020-03-10
Developer
Utility / transmission ownerEl Paso Electric Company

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.