Stern Solar (1198)

Stern Solar is a 20.0 MW solar interconnection project in Renssalear, New York with a current status of withdrawn. It is proposed to connect at Battenkill - Schaghticoke 115kV.

20.0 MWCapacity
WithdrawnStatus
FMarket
SolarTechnology

Project facts

Canonical nameStern Solar
Queue ID1198
Statuswithdrawn
Source status0
MarketF
TechnologySolar
Capacity20.0 MW
StateNew York
CountyRenssalear
Point of interconnectionBattenkill - Schaghticoke 115kV
Requested (queue) date2021-06-09
Proposed in-service date2024-11-30
Operational date
Withdrawn date
DeveloperGranada Solar, LLC
Utility / transmission ownerNM-NG

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-13new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata