Stewarts Bridge Hydro (0355)

Stewarts Bridge Hydro is a 3.0 MW other interconnection project in Saratoga, New York with a current status of operational. It is proposed to connect at Spier Falls - EJ West 115kV.

3.0 MWCapacity
OperationalStatus
FMarket
OtherTechnology

Project facts

Canonical nameStewarts Bridge Hydro
Queue ID0355
Statusoperational
Source status14
MarketF
TechnologyOther
Capacity3.0 MW
StateNew York
CountySaratoga
Point of interconnectionSpier Falls - EJ West 115kV
Requested (queue) date2010-08-03
Proposed in-service date—
Operational date—
Withdrawn date—
DeveloperBrookfield Renewable Power
Utility / transmission ownerNM-NG

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.