Stink Run - Sundial 138 kV is a 80.0 MW solar interconnection project in N/a, West Virginia with a current status of active.

80.0 MWCapacity
ActiveStatus
—Market
SolarTechnology

Project facts

Canonical nameStink Run - Sundial 138 kV
Queue IDAG2-568 - moved to TC2
Statusactive
Source statusActive
Market—
TechnologySolar
Capacity80.0 MW
StateWest Virginia
CountyN/a
Point of interconnection—
Requested (queue) date2021-03-31
Proposed in-service date2028-12-31
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerAEP

What changed

ObservedFieldOld valueNew valueMateriality
2026-10-01proposed_online_date—2028-12-31medium
2026-07-29new_project—activehigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata