Stoneboro-Perry 69 kV (AG2-249 - moved to TC2)

Stoneboro-Perry 69 kV is a 20.0 MW solar interconnection project in Mercer, Pennsylvania with a current status of withdrawn.

20.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameStoneboro-Perry 69 kV
Queue IDAG2-249 - moved to TC2
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity20.0 MW
StatePennsylvania
CountyMercer
Point of interconnection
Requested (queue) date2021-03-17
Proposed in-service date2027-12-01
Operational date
Withdrawn date2025-12-02
Developer
Utility / transmission ownerATSI

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.