Stringtown-Greenville/North 115kV Transmission Line (J3126)

Stringtown-Greenville/North 115kV Transmission Line is a 200.0 MW solar interconnection project in Washington, Mississippi with a current status of withdrawn. It is proposed to connect at Stringtown-Greenville/North 115kV Transmission Line.

200.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameStringtown-Greenville/North 115kV Transmission Line
Queue IDJ3126
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity200.0 MW
StateMississippi
CountyWashington
Point of interconnectionStringtown-Greenville/North 115kV Transmission Line
Requested (queue) date2022-09-14
Proposed in-service date2026-10-01
Operational date2026-10-01
Withdrawn date2025-07-30
Developer
Utility / transmission ownerENTERGY ARKANSAS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata