Sullivan 345kV (AH1-085)

Sullivan 345kV is a 500.0 MW other interconnection project with a current status of withdrawn.

500.0 MWCapacity
WithdrawnStatus
Market
OtherTechnology

Project facts

Canonical nameSullivan 345kV
Queue IDAH1-085
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyOther
Capacity500.0 MW
StateN/A
CountyN/a
Point of interconnection
Requested (queue) date2021-07-30
Proposed in-service date2025-12-31
Operational date
Withdrawn date2024-11-23
Developer
Utility / transmission ownerAEP

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-28

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata