Sunbury #2 500kV (AB2-074)

Sunbury #2 500kV is a 113.0 MW gas interconnection project in Snyder, Pennsylvania with a current status of withdrawn.

113.0 MWCapacity
WithdrawnStatus
Market
GasTechnology

Project facts

Canonical nameSunbury #2 500kV
Queue IDAB2-074
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyGas
Capacity113.0 MW
StatePennsylvania
CountySnyder
Point of interconnection
Requested (queue) date2016-04-01
Proposed in-service date2019-09-02
Operational date
Withdrawn date2020-05-04
Developer
Utility / transmission ownerPPL

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.