SUNC Spearville - Holcomb 345kV (GEN-2021-069)
SUNC Spearville - Holcomb 345kV is a 249.6 MW wind interconnection project in Hodgeman And Ford, Kansas with a current status of active. It is proposed to connect at SUNC Spearville - Holcomb 345kV.
249.6 MWCapacity
ActiveStatus
KSMarket
WindTechnology
Project facts
| Canonical name | SUNC Spearville - Holcomb 345kV |
|---|---|
| Queue ID | GEN-2021-069 |
| Status | active |
| Source status | IA FULLY EXECUTED/ON SCHEDULE |
| Market | KS |
| Technology | Wind |
| Capacity | 249.6 MW |
| State | Kansas |
| County | Hodgeman And Ford |
| Point of interconnection | SUNC Spearville - Holcomb 345kV |
| Requested (queue) date | 2021-04-26 |
| Proposed in-service date | 2030-09-15 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | SUNC |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | active | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata