Sunnyside 345kV (GEN-2017-167)

Sunnyside 345kV is a 52.0 MW battery interconnection project in Carter, Oklahoma with a current status of withdrawn. It is proposed to connect at Sunnyside 345kV.

52.0 MWCapacity
WithdrawnStatus
OKMarket
BatteryTechnology

Project facts

Canonical nameSunnyside 345kV
Queue IDGEN-2017-167
Statuswithdrawn
Source statusTERMINATED
MarketOK
TechnologyBattery
Capacity52.0 MW
StateOklahoma
CountyCarter
Point of interconnectionSunnyside 345kV
Requested (queue) date2017-11-29
Proposed in-service date2027-12-31
Operational date
Withdrawn date2024-09-06
Developer
Utility / transmission ownerOGE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata