Sweatt (2048_A)

Sweatt is a 41.9 MW gas interconnection project in Lauderdale, Mississippi with a current status of operational.

41.9 MWCapacity
OperationalStatus
SOCOMarket
GasTechnology

Project facts

Canonical nameSweatt
Queue ID2048_A
Statusoperational
Source status(OP) Operating
MarketSOCO
TechnologyGas
Capacity41.9 MW
StateMississippi
CountyLauderdale
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date1971-05-01
Withdrawn date—
Developer—
Utility / transmission ownerMississippi Power Co

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—operationalhigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata