Talawanda to C-River 138kV (GEN-2021-065)

Talawanda to C-River 138kV is a 200.0 MW solar interconnection project in Pittsburg, Oklahoma with a current status of withdrawn. It is proposed to connect at Talawanda to C-River 138kV.

200.0 MWCapacity
WithdrawnStatus
OKMarket
SolarTechnology

Project facts

Canonical nameTalawanda to C-River 138kV
Queue IDGEN-2021-065
Statuswithdrawn
Source statusWITHDRAWN
MarketOK
TechnologySolar
Capacity200.0 MW
StateOklahoma
CountyPittsburg
Point of interconnectionTalawanda to C-River 138kV
Requested (queue) date2021-04-28
Proposed in-service date2026-10-01
Operational date
Withdrawn date2022-12-15
Developer
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata