Taos Mesa Energy Facility Hybrid (63728_BESS)

Taos Mesa Energy Facility Hybrid is a 12.5 MW battery interconnection project in Taos, New Mexico with a current status of operational.

12.5 MWCapacity
OperationalStatus
PNMMarket
BatteryTechnology

Project facts

Canonical nameTaos Mesa Energy Facility Hybrid
Queue ID63728_BESS
Statusoperational
Source status(OP) Operating
MarketPNM
TechnologyBattery
Capacity12.5 MW
StateNew Mexico
CountyTaos
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date2022-11-01
Withdrawn date—
Developer—
Utility / transmission ownerTaos Mesa Energy Facility, LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—operationalhigh

Explore related data

Source last checked2026-11-01
Data last materially changed2026-11-01
Page data generated2026-11-26

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.