TBD is a 199.0 MW battery interconnection project in Spokane, Washington with a current status of active. It is proposed to connect at Bluebird 230kV Station.
199.0 MWCapacity
ActiveStatus
WAMarket
BatteryTechnology
Project facts
| Canonical name | TBD |
|---|---|
| Queue ID | CS26-01 |
| Status | active |
| Source status | Cluster Study |
| Market | WA |
| Technology | Battery |
| Capacity | 199.0 MW |
| State | Washington |
| County | Spokane |
| Point of interconnection | Bluebird 230kV Station |
| Requested (queue) date | 2026-03-26 |
| Proposed in-service date | 2029-12-09 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Avista Utilities |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-03 | new_project | — | active | high |
Explore related data
Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27
Provenance: avista-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.