TC-Eva Texas County 69kV (GEN-2009-073T)
TC-Eva Texas County 69kV is a 46.5 MW wind interconnection project in Texas County, Oklahoma with a current status of withdrawn. It is proposed to connect at TC-Eva Texas County 69kV.
46.5 MWCapacity
WithdrawnStatus
OKMarket
WindTechnology
Project facts
| Canonical name | TC-Eva Texas County 69kV |
|---|---|
| Queue ID | GEN-2009-073T |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | OK |
| Technology | Wind |
| Capacity | 46.5 MW |
| State | Oklahoma |
| County | Texas County |
| Point of interconnection | TC-Eva Texas County 69kV |
| Requested (queue) date | — |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | 2013-07-22 |
| Developer | — |
| Utility / transmission owner | SPS |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata