Tecumseh 230kV Substation (GEN-2017-193)
Tecumseh 230kV Substation is a 201.6 MW solar interconnection project in Shawnee, Kansas with a current status of withdrawn. It is proposed to connect at Tecumseh 230kV Substation.
201.6 MWCapacity
WithdrawnStatus
KSMarket
SolarTechnology
Project facts
| Canonical name | Tecumseh 230kV Substation |
|---|---|
| Queue ID | GEN-2017-193 |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | KS |
| Technology | Solar |
| Capacity | 201.6 MW |
| State | Kansas |
| County | Shawnee |
| Point of interconnection | Tecumseh 230kV Substation |
| Requested (queue) date | 2017-11-30 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | 2022-09-21 |
| Developer | — |
| Utility / transmission owner | WERE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata