Three Rivers Energy Storage (1487)

Three Rivers Energy Storage is a 80.0 MW battery interconnection project in Onondaga, New York with a current status of withdrawn. It is proposed to connect at Curtis Street - Teall 115 kV Line #13.

80.0 MWCapacity
WithdrawnStatus
CMarket
BatteryTechnology

Project facts

Canonical nameThree Rivers Energy Storage
Queue ID1487
Statuswithdrawn
Source status0
MarketC
TechnologyBattery
Capacity80.0 MW
StateNew York
CountyOnondaga
Point of interconnectionCurtis Street - Teall 115 kV Line #13
Requested (queue) date2022-12-22
Proposed in-service date2024-07-31
Operational date
Withdrawn date
DeveloperACE DEVCO NC, LLC
Utility / transmission ownerNM-NG

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.