Titan Smith Street (0105)

Titan Smith Street is a 79.9 MW gas interconnection project in Kings, New York with a current status of withdrawn. It is proposed to connect at Gowanus 138 or 345 kV.

79.9 MWCapacity
WithdrawnStatus
Market
GasTechnology

Project facts

Canonical nameTitan Smith Street
Queue ID0105
Statuswithdrawn
Source status0
Market
TechnologyGas
Capacity79.9 MW
StateNew York
CountyKings
Point of interconnectionGowanus 138 or 345 kV
Requested (queue) date2001-10-05
Proposed in-service date2019-03-06
Operational date
Withdrawn date
DeveloperCalpine Energy Services, L.P.
Utility / transmission ownerCONED

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.