Tower Hill Substation - Western RI DER Study #3 (1590)

Tower Hill Substation - Western RI DER Study #3 is a 3.1 MW solar interconnection project in Washington, Rhode Island with a current status of withdrawn. It is proposed to connect at RIE Feeder 88F7, Tower Hill Substation.

3.1 MWCapacity
WithdrawnStatus
RIMarket
SolarTechnology

Project facts

Canonical nameTower Hill Substation - Western RI DER Study #3
Queue ID1590
Statuswithdrawn
Source statusW
MarketRI
TechnologySolar
Capacity3.1 MW
StateRhode Island
CountyWashington
Point of interconnectionRIE Feeder 88F7, Tower Hill Substation
Requested (queue) date2024-08-19
Proposed in-service date2026-12-31
Operational date
Withdrawn date2025-06-13
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata