Tupelo 138kV substation (ASGI-2015-006)

Tupelo 138kV substation is a 9.0 MW solar interconnection project in Coal County, Oklahoma with a current status of withdrawn. It is proposed to connect at Tupelo 138kV substation.

9.0 MWCapacity
WithdrawnStatus
OKMarket
SolarTechnology

Project facts

Canonical nameTupelo 138kV substation
Queue IDASGI-2015-006
Statuswithdrawn
Source statusTERMINATED
MarketOK
TechnologySolar
Capacity9.0 MW
StateOklahoma
CountyCoal County
Point of interconnectionTupelo 138kV substation
Requested (queue) date2015-09-29
Proposed in-service date2016-03-03
Operational date
Withdrawn date2020-04-23
Developer
Utility / transmission ownerSWPA

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata