Upper Falls Solar (1475)

Upper Falls Solar is a 46.0 MW other interconnection project in Wyoming, New York with a current status of withdrawn. It is proposed to connect at Line 907 Substation 162, Alleghany (S1185) and Houghton Substation (S180). 115kV.

46.0 MWCapacity
WithdrawnStatus
BMarket
OtherTechnology

Project facts

Canonical nameUpper Falls Solar
Queue ID1475
Statuswithdrawn
Source status0
MarketB
TechnologyOther
Capacity46.0 MW
StateNew York
CountyWyoming
Point of interconnectionLine 907 Substation 162, Alleghany (S1185) and Houghton Substation (S180). 115kV
Requested (queue) date2022-11-29
Proposed in-service date2024-05-31
Operational date
Withdrawn date
DeveloperSR1 Shift NY I
Utility / transmission ownerRG&E

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.