Vernon Repowering (162)

Vernon Repowering is a 32.0 MW other interconnection project in Windham, Vermont with a current status of operational.

32.0 MWCapacity
OperationalStatus
VTMarket
OtherTechnology

Project facts

Canonical nameVernon Repowering
Queue ID162
Statusoperational
Source statusC
MarketVT
TechnologyOther
Capacity32.0 MW
StateVermont
CountyWindham
Point of interconnection
Requested (queue) date2006-07-18
Proposed in-service date
Operational date2008-03-13
Withdrawn date
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata