VS75SB (LG-22-9-7)

VS75SB is a 75.0 MW solar+battery interconnection project in Dona Ana, New Mexico with a current status of suspended. It is proposed to connect at Salopek-Vado 115kV line.

75.0 MWCapacity
SuspendedStatus
NMMarket
Solar+BatteryTechnology

Project facts

Canonical nameVS75SB
Queue IDLG-22-9-7
Statussuspended
Source statusSUSPENDED
MarketNM
TechnologySolar+Battery
Capacity75.0 MW
StateNew Mexico
CountyDona Ana
Point of interconnectionSalopek-Vado 115kV line
Requested (queue) date2022-09-30
Proposed in-service date2026-12-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerEl Paso Electric Company

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectsuspendedhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: epe-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata