WA Queue Project 45 — Wind in Kittitas County, Washington

WA Queue Project 45 — Wind in Kittitas County, Washington is a 80.0 MW wind interconnection project in Kittitas County, Washington with a current status of withdrawn. It is proposed to connect at Cascade-Rocky Reach 230kV Line.

80.0 MWCapacity
WithdrawnStatus
WAMarket
WindTechnology

Project facts

Canonical nameWA Queue Project 45 — Wind in Kittitas County, Washington
Queue ID45
Statuswithdrawn
Source statusWithdrawn
MarketWA
TechnologyWind
Capacity80.0 MW
StateWashington
CountyKittitas County
Point of interconnectionCascade-Rocky Reach 230kV Line
Requested (queue) date2015-10-29
Proposed in-service date2029-03-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerPuget Sound Energy

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: pse-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata