WA Queue Project G0665 — Wind in Garfield, Washington is a 750.0 MW wind interconnection project in Garfield, Washington with a current status of withdrawn. It is proposed to connect at Lower Granite 500kV or Central Ferry 500kV or Central Ferry 230kV.

750.0 MWCapacity
WithdrawnStatus
WAMarket
WindTechnology

Project facts

Canonical nameWA Queue Project G0665 — Wind in Garfield, Washington
Queue IDG0665
Statuswithdrawn
Source statusWITHDRAWN
MarketWA
TechnologyWind
Capacity750.0 MW
StateWashington
CountyGarfield
Point of interconnectionLower Granite 500kV or Central Ferry 500kV or Central Ferry 230kV
Requested (queue) date2020-12-22
Proposed in-service date2025-12-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerBonneville Power Administration

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata