WA Queue Project G1099 — Battery in Franklin, Washington

WA Queue Project G1099 — Battery in Franklin, Washington is a 25.0 MW battery interconnection project in Franklin, Washington with a current status of active. It is proposed to connect at Railroad Avenue Substation.

25.0 MWCapacity
ActiveStatus
WAMarket
BatteryTechnology

Project facts

Canonical nameWA Queue Project G1099 — Battery in Franklin, Washington
Queue IDG1099
Statusactive
Source statusRECEIVED
MarketWA
TechnologyBattery
Capacity25.0 MW
StateWashington
CountyFranklin
Point of interconnectionRailroad Avenue Substation
Requested (queue) date2026-07-14
Proposed in-service date2028-10-02
Operational date
Withdrawn date
Developer
Utility / transmission ownerBonneville Power Administration

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.